Question: An activity has these time estimates: optimistic = 4, most likely = 7, and pessimistic = 14. write down Its expected time. (Give your answer
An activity has these time estimates: optimistic = 4, most likely = 7, and pessimistic = 14. write down Its expected time. (Give your answer to two decimal places)