Question: QUESTION 5 Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for Dis 9. Earliest finish time

QUESTION 5 Activity D on a CPM network has

QUESTION 5 Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for Dis 9. Earliest finish time of B is 25 and earliest finish time of C is 31. Latest start time of Fis 46. Write down the slack for F. 2 points QUESTION 6 An activity has these time estimates: optimistic = 5, most likely = 8, and pessimistic = 15. write down Its expected time. (Give your answer to two decimal places) 1 points