Question: A can do a work in 20 days, while B can do the same work in 10 days. A work for 4 days and
A can do a work in 20 days, while B can do the same work in 10 days. A work for 4 days and B works for 5 days and leaves the work. The remaining work is done by C in 3 days. In how many days A, B and C working together can complete the work ? 04 O 6 03 05
Step by Step Solution
There are 3 Steps involved in it
The detailed ... View full answer