Question: A certain process starts from the station 1 and move through stations 2,3,4, and ends with the station 5. Customer demand is 80 units per
A certain process starts from the station 1 and move through stations 2,3,4, and ends with the station 5. Customer demand is 80 units per hour. Capacities in each station are: Station 1: 45 seconds, station 2: 32 seconds, station 3: 38 seconds, station 4: 50 seconds, station 5: 42 seconds. Which of the following statement is true?
1-The process cant meet the customer demand
2-The process can meet the customer demand
3-To improve the process they should change the station 2
4-Both B) and C) are correct
Both A) and C) are correct