Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C - D A, B E B F C, E

A certain project has the following precedence relationships.

Activity Immediate Predecessor(s)
A -
B -
C -
D A, B
E B
F C, E
G D, E
H F, G

The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.

Activity Optimistic (a) Most Likely (m) Pessimistic (b)
A 2 6 8
B 6 8 12
C 4 9 15
D 4 5 8
E 2 5 11
F 6 7 9
G 2 4 7
H 3 7 7

Suppose you have a personal goal of completing this project in 32 weeks.

What is the probability that you will be able to meet this goal?