Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C - D A, B E B F C, E
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | - |
| D | A, B |
| E | B |
| F | C, E |
| G | D, E |
| H | F, G |
The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.
| Activity | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
|---|---|---|---|
| A | 2 | 6 | 8 |
| B | 6 | 8 | 12 |
| C | 4 | 9 | 15 |
| D | 4 | 5 | 8 |
| E | 2 | 5 | 11 |
| F | 6 | 7 | 9 |
| G | 2 | 4 | 7 |
| H | 3 | 7 | 7 |
What is the critical path, and how long is this project expected to last? Show all your work.