Question: A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. Case Probability
A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below.
Case Probability NPV Worse 0.30 ($43.10) Base (likely) 0.50 $10.40 Best 0.20 $63.90
How much is the "Expected NPV" (net present value) of this project (in millions)? Enter your answer in the following format: + or - 1.23;
Hint: Answer is between 4.49 and 5.56
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock