Question: A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. Case Probability
| A company is evaluating a new project. |
| The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. |
| Case | Probability | NPV |
| Worse | 0.30 | ($43.10) |
| Base (likely) | 0.50 | $10.40 |
| Best | 0.20 | $63.90 |
| How much is the "Standard deviation of the NPV" (net present value) of this project (in millions)? |
| Enter your answer in the following format: 12.34; Hint: Answer is between 33.33 and 40.45 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
