Question: A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. Case Probability
A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. Case Probability NPV Worse 0.30 ($43.10) Base (likely) 0.50 $10.40 Best 0.20 $63.90 How much is the "Standard deviation of the NPV" (net present value) of this project (in millions)? Enter your answer in the following format: 12.34; Hint: Answer is between 33.33 and 40.45