Question: A company is evaluating a new project. The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. Case Probability
| A company is evaluating a new project. |
| The project's NPV (in millions) under various economic scenarios and those scenario probabilities are shown below. |
| Case | Probability | NPV |
| Worse | 0.20 | ($43.10) |
| Base (likely) | 0.50 | $10.40 |
| Best | 0.30 | $63.90 |
| How much is the "Expected NPV" (net present value) of this project (in millions)? |
| Enter your answer in the following format: + or - 123.45; Hint: Answer is between 14.33 and 17.48 |