Question: A computer - system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Immediate Activity Activity Predecessor
A computersystem installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
Immediate Activity
Activity Predecessors Time
A
B
C
A
D
B C
E
C D
F
E
G
B
H
F G
What is the project completion time? Round your answer to the nearest whole number.
weeks