Question: a ) Construct a Logic Network diagram ( A @ A or AoN ) for the following project activities. b ) Find Early Start (
a Construct a Logic Network diagram @ or AoN for the following project activities.
b Find Early Start ES Early Finish EF Late Start LS and Late Finish LF and Total Float TF of all the activities. Solve the network in terms of "Calendar Dates". Activity A is supposed to start on of November,
c Find duration of the project in days and mark also Critical Path CP on the Network.
d Draw Bar chart. Draw bar chart wrt Calendar dates. Activity A is supposed to start on of November,
tableActivityDuration,PredecessorsF days,NoneB days,AC days,AD days,AE days,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
