Question: Construct a PERT/CPM network diagram for a project having the following activities; ------------------------------------------------------------------------------------------- Activities Lead Duration/ Cost Activities Weeks ------------------------------------------------------------------------------------------- A - 4 20,000 B

  1. Construct a PERT/CPM network diagram for a project having the following activities;

-------------------------------------------------------------------------------------------

Activities Lead Duration/ Cost

Activities Weeks

-------------------------------------------------------------------------------------------

A - 4 20,000

B - 2 10,000

C - 3 15,000

D A 2 12000

E B 2 16,000

F C 3 21,000

G D,E 2 20,000

H F 3 30,000

I D,E 2 7,000

J I, H 2 12,000

K G 2 10,000

L K,J 3 9,000

----------------------------------------------------------------------------------------------

  1. How long will it take to complete this project?
  2. Identify critical path for this project.

Compare the weekly costs using Earlier Start (ES) Earlier Finish (EF), with Last Start (LS) Last Finish (LF).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!