Question: Construct a PERT/CPM network diagram for a project having the following activities; ------------------------------------------------------------------------------------------- Activities Lead Duration/ Cost Activities Weeks ------------------------------------------------------------------------------------------- A - 4 20,000 B
- Construct a PERT/CPM network diagram for a project having the following activities;
-------------------------------------------------------------------------------------------
Activities Lead Duration/ Cost
Activities Weeks
-------------------------------------------------------------------------------------------
A - 4 20,000
B - 2 10,000
C - 3 15,000
D A 2 12000
E B 2 16,000
F C 3 21,000
G D,E 2 20,000
H F 3 30,000
I D,E 2 7,000
J I, H 2 12,000
K G 2 10,000
L K,J 3 9,000
----------------------------------------------------------------------------------------------
- How long will it take to complete this project?
- Identify critical path for this project.
Compare the weekly costs using Earlier Start (ES) Earlier Finish (EF), with Last Start (LS) Last Finish (LF).