Question: Construct a PERT/CPM network diagram for a project having the following activities; ------------------------------------------------------------------------------------------- Activities Lead Duration/ Cost Activities Weeks ------------------------------------------------------------------------------------------- A - 4 20,000 B

  1. Construct a PERT/CPM network diagram for a project having the following activities;

-------------------------------------------------------------------------------------------

Activities Lead Duration/ Cost

Activities Weeks

-------------------------------------------------------------------------------------------

A - 4 20,000

B - 2 10,000

C - 3 15,000

D A 2 12000

E B 2 16,000

F C 3 21,000

G D,E 2 20,000

H F 3 30,000

I D,E 2 7,000

J I, H 2 12,000

K G 2 10,000

L K,J 3 9,000

----------------------------------------------------------------------------------------------

a. Compare the weekly costs using Earlier Start (ES) Earlier Finish (EF), with Last Start (LS) Last Finish (LF).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!