A contract requirement state that a project must be completed within 210 working days or it will incur penalties for late completion. Analysis of the activity network reveals an expected or mean project time of 175 working days with the standard deviation of the critical path equal to 20.
A. what is the probability that the project will be completed before the 210 day deadline?
B. when is the above firm 96% confident of completing the project?