Question: a. Design the Project network image using the Activity on Arrow (AOA) approach for the Redblack! b. Determine the Critical Path and what are the
a. Design the Project network image using the Activity on Arrow (AOA) approach for the Redblack! b. Determine the Critical Path and what are the implications for the project! c. Calculate Project Completion Time! d. Define ES, EF, LS, LF and Slack!

Aktivitas Aktivitas Waktu Pendahulu (Minggu) A 3 B A 4 A 2. D 3 E 3 F B, E 7 G D 4 C G 7 I BE 5 J D 5 K HI 8 L J, K 8 M F, L 4