Question: a) Determine the earliest start time, earliest finish time, latest start time, latest finish time, and slack time for each activity. b) Identify the critical
a) Determine the earliest start time, earliest finish time, latest start time, latest finish time, and slack time for each activity.
Given the following network diagram for a project (activity times are in days): 15 2. un 9 6 17 8 6 1 1 3 6 13 00 5 12 9 4 7
b) Identify the critical path.
c) What is the expected project duration?
d) If the project duration must be reduced by 3 days, which activities will most likely be affected?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
