Question: A Project is planned as shown below Activities A and B can begin with the start of the project. With the completion of Activities G
A Project is planned as shown below
Activities A and B can begin with the start of the project. With the completion of Activities G and J, the project ends. The project Starting Date is the date of this examination. Saturdays and Sundays are holidays and there are no public holidays.
Using MS Projects draw the Project Diagram and analyse the project, to determine the Earliest Start Time, Earliest Finish Time and Free Floats (also called Slacks) of each activity. Identify the Critical Activities and the Critical Path.
Activity Duration (days) Preceding Activity Resource Resource Requirement PQR Requirement XYZ 2 2 6 1 1 3 4 5 8 1 1 A B C D E F G H 2 1 7 2 A A B B C D E F I, H 7 2 0 3 2 1 0 2 8 3 - 1 1 J 7Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
