Question: a) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project.
-
a) Determine the expected completion time and variance for each activity.
-
b) Determine the total project completion time and the critical path for the project.
-
c) Determine ES, EF, LS, LF, and slack for each activity.
-
d) What is the probability that Kelle Carpet and Trim will finish

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts