Question: a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d)What is the

a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
d)What is the slack time for each individual activity?
Project Schedule: CODE ACTIVITY IMMEDIATE PREDECESSOR A DURATION (hours) 40 min 20 min 15 min B A C B D 1 hour 15 min Left Home and went to the Shop Dealing with the customer Making a list of the things customer wants Going to the godown from the shop Verifying the inventory and gathering the things customer wants Packaging the items Leaving the shop with the goods/items packed E B,C 40 min F D.E F 30 min 1 hr 15 mins GStep by Step Solution