Question: a. Develop the Gantt Chart b. Develop Critical Path Network c. Identify the Critical Path Activities d. Find float for each project activity Activity Predecessor

a. Develop the Gantt Chart b. Develop Critical

a. Develop the Gantt Chart b. Develop Critical Path Network c. Identify the Critical Path Activities d. Find float for each project activity Activity Predecessor Duration A 1 B A 3 A 1 D B,C 1 E D 1 F D 3 G D 3 H G 1 I FH 1.5 J 1 K I 3 L K 2