Question: a. Draw the Gantt Chart b. Develop Critical Path Network c. Determine the Project Duration d. Identify the Critical Path Activities e. Determine float for
a. Draw the Gantt Chart b. Develop Critical Path Network c. Determine the Project Duration d. Identify the Critical Path Activities e. Determine float for each project activity

ACTIVITY NAME IMMEDIATE PREDECESSOR DURATION (monts) A B E> 1 3 A A 1 D B,C 1 E A 1 F D 3 G Market analysis Product design Manufacturing study Select best product design Detailed marketing plans Manufacturing process Detailed product design Test prototype Finalize product design Order components Order production equipment Install production equipment D 3 H G 1 I I F,H 1.5 J I 1 K I 3 L K N