Question: a) Draw the Activity-on-Node (A-o-N) network assuming all days are working days. b) Identify critical path(s) and the project duration using CPM. c) What happens

a) Draw the Activity-on-Node (A-o-N) network assuming all days are working days. b) Identify critical path(s) and the project duration using CPM. c) What happens if Activity D delays for 2 days? d) What happens if Activity C delays for 11 days? Activity Duration Predecessor(s) (days) 10 A B 15 C 12 D 16 Can start 10 days after the finish of A Can start immediately after the finish of A Can start 2 days after the finish of B Can start 5 days after the finish of C Can start 15 days after the finish of D Can start 10 days after the finish of D Can start 8 days after the finish of E Can start 6 days after the finish of F E 21 17 F G 8