Question: a) Earned Value Management (EVM) integrates the project scope, cost, and schedule for assessing and measuring the project performance that compares the amount of work

a) Earned Value Management (EVM) integrates the project scope, cost, and schedule for assessing and measuring the project performance that compares the amount of work that was planned with the work that was completed or "earned. i. Assess with justification the progress of Project S and Project T. [16 marks] Table Q2(a) PV AC Project EV S 1000 600 750 T 450 600 800 ii. As a Project Manager, determine TWO (2) solutions (if required) based on the progress obtained in a) i) [4 marks]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
