Question: a) Earned Value Management (EVM) integrates the project scope, cost, and schedule for assessing and measuring the project performance that compares the amount of
a) Earned Value Management (EVM) integrates the project scope, cost, and schedule for assessing and measuring the project performance that compares the amount of work that was planned with the work that was completed or "earned". i. Assess with justification the progress of Project S and Project T. [16 marks] Table Q2(a) Project PV AC EV S 1000 600 750 T 450 600 800 ii. As a Project Manager, determine TWO (2) solutions (if required) based on the progress obtained in a) i) [4 marks]