Question: A facility conducts three - day programs and operates 7 days per week. A new batch of 4 0 0 starts a program on each

A facility conducts three-day programs and operates 7 days per week. A new
batch of 400 starts a program on each day of the week except Saturday and
Sunday (A person joining on Monday will leave on Thursday; one joining on
Tuesday will leave on Friday and so on). Assume that January 1 is a Monday
and the facility is just opening after a long Christmas break.
M1
10 min
M2
10 min
M3
2 min
M4
4 min
MBC 635 Operations & Supply Chain Management
---------------------------------------------------------------------------------------------------------------------------------
32/35
A.(3 points) Complete all entries in the table below.
Day Joining Leaving
Total in
the
System
Monday 400-400
Tuesday 400-800
Wednesday 400-1200
Thursday 400400
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Using data in week 2(from the 2nd Monday to Sunday, shaded), answer the
following parts.
B.(2 points) What is the average flow rate per day?
C.(1 point) What is the average flow time (MLT)?
D.(2 points) What is the (average) WIP?
E.(2 points) Now apply Little's law to the process and show that the left-hand
side of the equation is equal to the right-hand side.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!