Question: A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates. What is the probability

 A given project's expected duration along its critical path is 50

A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates. What is the probability that the project will finish on or before 50 days. 0.50 0.00 0.25 1.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!