Question: A local project being analyzed by PERT has following activities. A ctivity Activity name Times Estimates Predecessor Optimistic time Most likely Pessimistic Design A 10
A local project being analyzed by PERT has following activities.
| Activity | Activity name | Times Estimates | Predecessor | ||
| Optimistic time | Most likely | Pessimistic | |||
| Design | A | 10 | 20 | 26 | NIL |
| Build prototype | B | 4 | 4 | 10 | A |
| Evaluate equipment | C | 4 | 6 | 14 | A |
| Test prototype | D | 2 | 3 | 4 | B |
| Produce report | E | 1 | 5 | 6 | C, D |
| Procedures arrangement | F | 7 | 8 | 9 | C, D |
| Presentation | G | 2 | 6 | 7 | F, E |
What is its expected activity time and variance for activity E?
Select one:
A. ET=5.5; V=1.00
B. ET=19.3; V=0.83
C. ET=3.0; V=0.11
D. ET=7.0; V=7.12
E. ET=4.5; V=0.69
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock