Question: A local project being analyzed by PERT has following activities. A ctivity Activity name Times Estimates Predecessor Optimistic time Most likely Pessimistic Design A 10

A local project being analyzed by PERT has following activities.

Activity Activity name Times Estimates Predecessor
Optimistic time Most likely Pessimistic
Design A 10 20 26 NIL
Build prototype B 4 4 10 A
Evaluate equipment C 4 6 14 A
Test prototype D 2 3 4 B
Produce report E 1 5 6 C, D
Procedures arrangement F 7 8 9 C, D
Presentation G 2 6 7 F, E

What is its expected activity time and variance for activity E