Question: a m 2. Given the table below: ACTIVITY A B C D E 2 3 1 2 1 2 1 1 3 2 4 4

a m 2. Given the table below: ACTIVITY A B C D E 2 3 1 2 1 2 1 1 3 2 4 4 2 4 2 b 3 4 3 6 7 9 11 3 F G H 1 a. Use the PERT from project management to determine the critical path. (indicate all your calculations clearly) [20]