Question: A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if

A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if the process mean is 1980 cc and standard deviation is 30 cc?

No, because, Cpk>1.

No, because Cp>1.

Yes, because Cp>1.

No, because, Cpk>1.

No, because Cpk<1.

2)The information for project X is shown below. What are the critical path and the completion time of the project?

Crashing Costs

Activity

Preceding

Normal Time

1st Week

2nd Week

K

8 weeks

$4100

L

K

6 weeks

3250

N

K

1 week

450

450

M

L

5 weeks

3000

3500

J

N

4 weeks

500

Q

J,M

6 weeks

4000

4000

KLMQ, 30 weeks

KNJQ, 25 weeks

KLMQ, 25 weeks

KLNMJQ: 25 weeks

KNJQ, 30 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!