Question: A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if
A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if the process mean is 1980 cc and standard deviation is 30 cc?
| No, because, Cpk>1. | ||
| No, because Cp>1. | ||
| Yes, because Cp>1. | ||
| No, because, Cpk>1. | ||
| No, because Cpk<1. |
2)The information for project X is shown below. What are the critical path and the completion time of the project?
| Crashing Costs | ||||
| Activity | Preceding | Normal Time | 1st Week | 2nd Week |
| K | 8 weeks | $4100 | ||
| L | K | 6 weeks | 3250 | |
| N | K | 1 week | 450 | 450 |
| M | L | 5 weeks | 3000 | 3500 |
| J | N | 4 weeks | 500 | |
| Q | J,M | 6 weeks | 4000 | 4000 |
| KLMQ, 30 weeks | ||
| KNJQ, 25 weeks | ||
| KLMQ, 25 weeks | ||
| KLNMJQ: 25 weeks | ||
| KNJQ, 30 weeks |