Question: A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if

A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if the process mean is 1980 cc and standard deviation is 30 cc? Question 39 options: No, because, Cpk>1. No, because Cpk<1. No, because, Cpk>1. Yes, because Cp>1. No, because Cp>1