Question: A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if
A manager wants to control a bottling process with upper and lower specification limits of 2100 cc and 1900 cc. Is the process capable if the standard deviation is 30 cc?
| No, because Cp<1. | ||
| No, because Cp>1. | ||
| We need to know the average of the process to answer the question. | ||
| Yes, because Cp>1. | ||
| Yes, because Cp<1. |
Step by Step Solution
There are 3 Steps involved in it