Question: A manufacturing company estimates semi-variable costs by using the high-low method with machine hours as the cost driver. Recent data are shown below. Period Costs
A manufacturing company estimates semi-variable costs by using the high-low method with machine hours as the cost driver. Recent data are shown below.
| Period | Costs | Machine Hours |
| 1 | ₱100,000 | 22,000 |
| 2 | 120,000 | 30,000 |
| 3 | 96,000 | 23,600 |
How much is the fixed component of the semi-variable cost?
Refer to Case 3
If 29,000 machine hours were budgeted for period 4, estimated semi-variable cost would total
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Using HighLow method variable cost is calculated as follows Variable ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
