Question: A new project will be scheduled based on the information given in Table 1. The following activities of the new project are listed with normal
A new project will be scheduled based on the information given in Table 1. The following activities of the new project are listed with normal time, crash time and the corresponding costs.

A. Determine the cost slope for the activity "A" in the given table.
B. Determine the cost slope for the activity "B" in the given table.
C. Determine the cost slope for the activity "G" in the given table.
D. Determine the cost slope for the activity "E" in the given table.
Cost Slope (RMday) (A) (B) Activity Precedent Normal Activity Time (days) A 5 B A 10 B 15 D B 14 E D 12 F B 8 G F 10 H C, E, G 4 I H 14 J I 5 Crash Time (days) 4 6 15 14 9 7 7 3 9 5 Normal Crash Cost Cost (RM) (RM) 40.000 42.000 120.000 200.000 62,000 62,000 90,000 90.000 80,000 90,500 70,000 78,000 93,000 | 123,000 42,000 44,000 210,000 220,000 31.000 31,000 D (E) (H) (1) Table 1Step by Step Solution