Question: A new project will be scheduled based on the information given in Table 1. The following activities of the new project are listed with normal
A new project will be scheduled based on the information given in Table 1. The following activities of the new project are listed with normal time, crash time and the corresponding costs.
(Please avoid using any additional formatting characters such as "," or "$" when you fill in blank answers.) (a) Draw a schedule AON network diagram to represent the project. (b) Determine the cost slope for the activity "B" in the given table.
(B) = ______ (c) Determine the project duration to complete the project.
The project duration to complete the project = ______ days