Question: A new scientific research centre has been constructed using NEC 4 ECC main Option E . The Project Manager certifies Completion on 0 1 May.
A new scientific research centre has been constructed using NEC ECC main Option E The Project Manager certifies Completion on May. The defects date is weeks after completion of the whole of the works. The Defect Correction period is weeks. Six weeks before the defects date, the Supervisor carries out an inspection