Question: A new scientific research centre has been constructed using NEC 4 ECC main Option E . The Project Manager certifies Completion on 0 1 May.

A new scientific research centre has been constructed using NEC4 ECC main Option E. The Project Manager certifies Completion on 01 May. The defects date is 52 weeks after completion of the whole of the works. The Defect Correction period is 4 weeks. Six weeks before the defects date, the Supervisor carries out an inspection