Question: A new scientific research centre has been constructed using NEC 4 ECC main Option E . The Project Manager certifies Completion on 0 1 May.
A new scientific research centre has been constructed using NEC ECC main Option E The Project Manager certifies Completion on May. The defects date is weeks after completion of the whole of the works. The Defect Correction period is weeks.
Which TWO of the following Statements are correct? Select TWO options:
A The contractor is required to submit its quality plan to the Project manager for acceptance at the intervals stated in the contract data.
B If the Contractor makes a change to its quality plan it should submit the revised plan to the supervisor for acceptance.