Question: A new scientific research centre has been constructed using NEC 4 ECC main Option E . The Project Manager certifies Completion on 0 1 May.

A new scientific research centre has been constructed using NEC4 ECC main Option E. The Project Manager certifies Completion on 01 May. The defects date is 52 weeks after completion of the whole of the works. The Defect Correction period is 4 weeks.
Which TWO of the following Statements are correct? Select TWO options:
A. The contractor is required to submit its quality plan to the Project manager for acceptance at the intervals stated in the contract data.
B. If the Contractor makes a change to its quality plan it should submit the revised plan to the supervisor for acceptance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!