Question: A partial information about a project is shown below. Activity M; 40 days; IP = G, H Activity N; 33 days; IP = G, H
A partial information about a project is shown below.
Activity M; 40 days; IP = G, H Activity N; 33 days; IP = G, H Activity P; 46 days; IP = K Activity Q; 62 days; IP = M Activity R; 40 days; IP = N, P It has been calculated that LF(Q) = 198 and LF(R) = 218.
Find the value of LF(G).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts