Question: Question 10 15 pts A partial information about a project is shown below. Activity M; 42 days: IP = G, H Activity N: 46 days:

Question 10 15 pts A partial information about a
Question 10 15 pts A partial information about a project is shown below. Activity M; 42 days: IP = G, H Activity N: 46 days: IP = GH Activity P: 32 days; IP = K Activity Q: 73 days; IP = M Activity R; 52 days: IP = NP It has been calculated that LF(Q) = 217 and LF(R) = 190. Find the value of LF(G)