Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Time Most Likely Time Pessimistic

A partially solved PERT problem is detailed in the table below. Times are given in weeks.

Activity

Immediate

Predecessor(s)

Optimistic Time

Most Likely Time

Pessimistic Time

A

--

5

11

14

B

-

3

3

9

C

--

6

10

14

D

A, B

3

5

7

E

B

4

6

11

F

C

6

8

13

G

D, E

2

4

6

H

F

3

3

9

I

G

2

4

6

J

H

4

7

9

K

I, J

4

7

8

a) Calculate the expected duration (D), and variance of each activity.

b) Calculate ES, EF, LS, LF, S for each activity.

Activity

ET

Variance

ES

EF

LS

LF

S

A

Answer

Answer

Answer

Answer

Answer

Answer

Answer

B

Answer

Answer

Answer

Answer

Answer

Answer

Answer

C

Answer

Answer

Answer

Answer

Answer

Answer

Answer

D

Answer

Answer

Answer

Answer

Answer

Answer

Answer

E

Answer

Answer

Answer

Answer

Answer

Answer

Answer

F

Answer

Answer

Answer

Answer

Answer

Answer

Answer

G

Answer

Answer

Answer

Answer

Answer

Answer

Answer

H

Answer

Answer

Answer

Answer

Answer

Answer

Answer

I

Answer

Answer

Answer

Answer

Answer

Answer

Answer

J

Answer

Answer

Answer

Answer

Answer

Answer

Answer

K

Answer

Answer

Answer

Answer

Answer

Answer

Answer

c) Which activities form the critical path? AnswerCFHJKADGIKBDGIKBEGIK
d) What is the estimated time of the critical path? Answer weeks
e) If the project is due to be completed in 34 weeks, what is the probability that the project will be completed on the due date? Answer %
f) If the project manager wants at least a 95% probability that the project will be completed on the due date, what is the shortest project due date that will satisfy the manager? Answer weeks

g) Which activity(ies) can be delayed 10.83 weeks without impacting the expected project completion date?

AnswerB and EB and CBEA and H
h) How many week(s) can you delay the activity D, without impacting the expected project completion date?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve the given PERT problem I will systematically address all parts with detailed explanation... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!