Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity ImmediatePredecessor(s) Optimistic Most Likely Pessimistic A 8 10

A partially solved PERT problem is detailed in
A partially solved PERT problem is detailed in
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity ImmediatePredecessor(s) Optimistic Most Likely Pessimistic A 8 10 15 11 B 7 8 9 A 5 6 10 D 3 3 3 E BD 1 5 9