Question: A PERT diagram for a project is given below: A=12 B=3 C=9 D=17 E=11 Assume that activity times of Start and End are zero. Activity
A PERT diagram for a project is given below:

A=12
B=3
C=9
D=17
E=11 Assume that activity times of Start and End are zero. Activity times for each activity is given in the data table below. a. Calculate each ? in the PERT diagram. (20 ?s, 0.3 pts each, 6 pts total) b. Determine the critical path.(1 pts)
A Start HD End ? -- B EStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
