Question: A Problem: A company is planning to buy a machine to process these products. How many machines should be bought? 1 machine means 1
A Problem: A company is planning to buy a machine to process these products. How many machines should be bought? 1 machine means 1 worker also!! Available Working time - 8 hrs. X 250 days in a year Calculate for single Shift Calculate for 2 - shift Calculate for 3 Shift Conclusion on the no. of machines Product A B C Annual Demand 400 300 700 Std. Processing Total Processing Time per unit (hr.)| Time Needed (hr.) 5 2000 8 2400 2 1400
Step by Step Solution
There are 3 Steps involved in it
Answer To determine the number of machines needed for processing the given products we need to calculate the total processing time required for each p... View full answer