Question: :A process chart is different than a time function mapping because it provides information on value added activities only provides the flow of the processo

:A process chart is different than a time

:A process chart is different than a time function mapping because it provides information on value added activities only provides the flow of the processo provides flow of the process with duration of the activities does not provide detail on value added activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock