Question: A process contains 2 steps. The duration of Activity A is 10 minutes and it uses Resource X. The duration of Activity B is 5
A process contains 2 steps. The duration of Activity A is 10 minutes and it uses Resource X. The duration of Activity B is 5 minutes and it uses Resource Y. What happens to capacity if I make an investment to reduce the activity time for Step B to 2 minutes but Activity A now takes 12 minutes?