Question: A process contains 2 steps. The duration of Activity A is 5 minutes and it uses Resource X. The duration of Activity B is 10
A process contains 2 steps. The duration of Activity A is 5 minutes and it uses Resource X. The duration of Activity B is 10 minutes and it uses Resource Y. What happens to capacity if I make an investment that reduces the activity time for Step B to 5 minutes?
A. Capacity doubles
B. Capacity becomes 6 jobs per min
c. Capacity is cut half because activity time is cut in half
D. Capacity rises but does not double because A still takes 5 mins
E. Capacity does not change