Question: A process contains 2 steps. The duration of Activity A is 5 minutes and uses Resources X. The duration of Activity B is 10 minutes
A process contains 2 steps. The duration of Activity A is 5 minutes and uses Resources X. The duration of Activity B is 10 minutes and it uses Resources Y. What happens to capacity if 1 make an investment to reduce the activity time for Shop B to 2 mins but Activity A now takes 12 minutes?
A. Capacity A increases from 1/10 to 1/12 jobs per min
B. Capacity increases from 1/(5+10) to 1/(2+12) jobs per min
C. Capacity increases from 4 jobs per min to 5 jobs per min
D. Capacity falls from 1/10 jobs per min to 1/12 jobs per min
E. Capacity does not change