Question: A process contains 2 steps. The duration of Activity A is 5 minutes and it uses Resource X. The duration of Activity B is 10
A process contains 2 steps. The duration of Activity A is 5 minutes and it uses Resource X. The duration of Activity B is 10 minutes and it uses Resource Y. What happens to capacity if I make an investment that reduces the activity time for Step B to 5 minutes but increases the activity time for Step A to 6 minutes?
A. Capacity doubles.
B. Capacity becomes 5 jobs per minute.
C. Capacity is cut in half because activity time is cut in half.
D. Capacity rises but does not double because Activity A becomes the bottleneck.
E. Capacity does not change.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock