Question: A product is to be processed from its raw form to finished form through a number of workstations. The production lead time is given
A product is to be processed from its raw form to finished form through a number of workstations. The production lead time is given as 3 days. The daily demand requirement is 500 units. Safety stock is required for one day. Container's capacity is 400 units. Determine the number of Kanbans (containers) required.
Step by Step Solution
There are 3 Steps involved in it
Step 1 Calculate the Total Lead Time Total Lead Time Production Lead Time Safety Time ... View full answer